AJOT | February 25, 2019 | Ports & Terminals | Ports
Port of Everett reaches major milestone on its Seaport Modernization with installation of the final steel pile to support a strengthened South Terminal. In total, 343 piles were set since the $36 million project kicked-off in summer 2018. Upland structural and utility work will continue throughout the year. The strengthened dock will be ready to support the next generation of over-dimensional cargo, including aerospace parts for the new 777X by December 2019.