Jumbo Offshore has completed the transportation and wet storage of a riser caisson for Technip FMC. Jumbo carried out the job in October, deploying its heavy-lift vessel Fairplayer to handle the 120-metre long and 1.3-metre diameter caisson.
The Fairplayer picked up the caisson from the Scottish port of Nigg, an operation that demanded a finely-tuned rigging arrangement due to the high flexibility of the caisson. To this end, each of the Fairplayer’s 900-tonne cranes used double slings and a total of five connection points.
The preparatory engineering of this project is also notable. Having worked together on numerous occasions in the past, Technip FMC and Jumbo Offshore have a good working relationship. For this riser caisson project, the two companies worked together on the project engineering. Technip FMC carried out the calculations for the rigging, and Jumbo worked on the vessel-specific calculations regarding the Fairplayer’s movement at different phases of the operation.
Once positioned on the seabed, Jumbo used an ROV to disconnect the caisson, leaving two rigging points in position to allow Technip FMC to pick it up for installation at a later date.
“This job involved the careful handling of fragile offshore equipment. But with our experienced crews and engineering teams, combined with the dual cranes of the Fairplayer, Jumbo Offshore had the technical capabilities and offshore expertise that made this precision operation a success,” notes Granneman. “Technip FMC is a very valued client of ours and we look forward to working with their team in the future.”