The Port of Long Beach is kicking off 2023 with plenty to celebrate. On Dec. 23, President Joe Biden signed into law the Water Resources Development Act (WRDA) of 2022, the biennial legislation authorizing federal flood control, navigation and ecosystem improvements that include the Port’s Channel Deepening Project.
“We are grateful to members of the House and Senate and the Army Corps of Engineers who championed this bill, the many lawmakers from both parties who voted for it and President Biden,” said Board of Harbor Commissioners President Sharon L. Weissman. “Their overwhelming support recognizes how vital international trade through the Port of Long Beach is to the U.S. economy.”
“This project will widen and deepen the harbor serving one of the world’s top 10 busiest container port complexes,” said Port Executive Director Mario Cordero. “Increasing the safety and efficiency of vessels transiting our waterways supports our mission to remain competitive while reducing pollution from port-related operations.”
The Port’s Channel Deepening Project has been in the works for more than eight years and is an essential component of the Port’s Master Plan. Key elements include deepening the Long Beach Approach Channel from 76 to 80 feet, easing turning bends in the Main Channel to deepen a wider area to 76 feet, deepening parts of the West Basin from 50 to 55 feet, constructing an approach channel and turning basin to Pier J South with a depth of 55 feet, improving the breakwaters at the entrance to Pier J, and depositing dredged material in nearshore sites for reuse or in federally approved ocean disposal sites.
The project’s operational benefits include more room for the largest tankers and container vessels to transit the harbor and fewer delays related to tidal flows. Deeper, wider channels also reduce the need for large vessels to transfer liquid bulk cargo or containers to smaller vessels before entering the harbor. The process, known as lightering, ensures large vessels have the underkeel clearance they need to move through the harbor as it is currently configured.
Environmental benefits include lower fuel consumption because ships will be able to maneuver more efficiently through the harbor. Burning less fuel reduces vessel pollution – emissions of particulate matter, nitrogen oxides and sulfur oxides.
The Port is sharing the cost of the $200 million project with the Corps, whose responsibilities include building and maintaining the nation’s waterways. Setting the stage for congressional authorization, the Corps issued a record of decision in July 2022 endorsing the project based on multiyear environmental and cost-benefit studies of project. The Corps concluded deepening and widening channels in the harbor would lead to improved vessel navigation, safety, and national economic benefits valued at more than $15 million annually. In September, the Long Beach Board of Harbor Commissioners certified the project’s companion environmental impact report.
The progress built on momentum from the 2021 Bipartisan Infrastructure Law, which reflected the project’s support from the Biden-Harris Administration by designating nearly $8 million for early planning, engineering and design work.
California Sens. Dianne Feinstein and Alex Padilla played key roles in shepherding WRDA through the legislative process, as did Rep. Alan Lowenthal, who serves on the House Transportation and Infrastructure Committee. Cordero appeared before the House committee in February to discuss the global importance of the project and urge Congress to advance it.
Lowenthal is retiring after five consecutive terms representing the 47th District, which includes Long Beach, Lakewood, Signal Hill and neighboring Orange County communities. A former Long Beach city councilman who served in both houses of the California Legislature before winning his congressional seat, Lowenthal has advocated for the region’s economic interests and environmental protection throughout his three decades in government.
Federal authorization of the Channel Deepening Project allows the Port and the Corps
to proceed with engineering agreements, detailed planning and budgets, bidding and awarding construction contracts and procuring funding. In the coming year, the Port and the Corps are expected to execute a design agreement and initiate the design work. Construction is projected to start in 2027 and take approximately three years.